Child pages
  • 2013 9/12 - 10/2 Sprint Checklist

This is a public wiki space. All contents are publicly accessible unless page restrictions are in place.

Skip to end of metadata
Go to start of metadata
TopicTasksResponsibleDependencies? (9/12)Completed?Blockers for Completion
Community building / process / organizationFinalize Product Stakeholder Group (PSG) membershipSherri YES 
 Establish a formal process/feedback loop for PSGSherri YES 
 Schedule and scope for a kick-off meeting/"orientation" for PSGSherri YES 
 Research techniques to improve process - e.g. "burn up" vs "burn down" listMark/Sherri/Brian YES 
Nuxeo trainingHave a date set and funding allocatedAdrianFundingPartial

Funding allocated

Waiting on Brendan re: scheduling

Metadata modelGet message out to PSG regarding metadata model feedback (object and collection level)AdrianPSG finalizedScheduledWill be presented at first PSG call
 Continue to research and test document type structuresAdrianTraining and consultationPartialMore needed on testing, with training
Content loadingSketch out a load schedule/profile clusters for Nuxeo with UCB staffBrian Scheduled 
 Obtain Halberstadt delicious food photos and METS from UC DavisBrian YES 
 Research Omeka exports in consultation with UCSFAdrian YES 
 Continue to receive and load collections from hard drivesBrian YES

UCSF is still out

UCSC wants one mailed

 Obtain and load Davis Yolo County aerial photo collection from MerrittAdrian YES 
 Test load content on stage through ETL process (platform importer)Brian/UCB

 

NOTime
Nuxeo installation / configurationContinue to research Nuxeo configuration templates for easier upgradesBrianTraining and consultationYES but unresolvedNeed training to fully understand how this works
 Complete process of setting up stage environmentBrian YESExcept for django on registry-stg - imminent
 Start set-up of production environmentBrianDelivery of prod. from unix groupNOStill waiting on tickets
Collection registryEstablish collection registry fields/elements for digitization pipeline: AggieSherri PartialHeather/Matt worked on schema generally but still need to hone in on specific fields for Aggie
 Create initial wireframe for collection record in Collection RegistrySherri YES - beyond 
 Create initial iteration of collection record for Collection RegistrySherri/Mark YES - beyond 
 Scope work for Amy in remaining sprint for AggieSherri/Brian YES 
HarvestingStart to scope out the harvest API in consultation with UCLA, UCSB, and UCSDMark Scheduled 
 Research Resource Sync  YES 
Public interfaceDemo/start to assess potential of Stanbol to drive topics and facets for public interfaceMarkBuilding stanbol on ec2 - yay!YES 
NEW TASKS     
Shibboleth-related stuffRe-ordered campus list for loginBrian YES 
 Switched to emails instead of EPPN for authenticationBrian YES 