Banana Slug Sprint Schedule | |
---|---|
Sprint | Status |
3/3/14 - 3/21/14 | completed |
3/24/14 - 4/11/14 | completed |
4/14/14 - 5/2/14 | completed |
5/5/14 - 5/23/14 | completed |
5/27/14 - 6/20/14 | completed |
6/23/14 - 7/11/14 (includes release communication period) | in process |
Task tracking for each sprint is available in Pivotal Tracker; to see tasks accomplished in a given sprint, click "more" --> "done" --> select dates of interest.
............
Banana Slug release plan | |
---|---|
Target end dateJune 30, 2014 | |
In a nutshellThe two major focuses of this release will be to a) open up the DAMS to campus library partners for new content and active editing and b) develop wireframes for the public interface. Depending on the velocities of these two sub-projects, we may stage them as separate releases. | |
Goals(by product component - see descriptions here) | |
DAMS |
|
Public Interface |
|
Collection Registry |
|
Central Index / API |
|
0
Working docs (project team only) |
---|
Meeting notes and agendas |
Communications planning / tracking |